Main Street reconstruction

The Main Street construction project that began in 2025 will continue into 2026, with work between Erin Drive and Elk Hill being rebuilt starting early May 2026. 

This work is driven by a 2024 geotechnical evaluation that identified the need to rehabilitate the road structure to maintain long-term safety and reliability on this key arterial route. The project includes full road reconstruction through a phased approach, intersection upgrades and improved pedestrian access.

This project is different from previous Main Street work north of Elk Hill, which focused on replacing underground utilities like water, sanitary and stormwater pipes.

Stage 4 of this year’s work includes milling the west southbound lane between Ridgegate Way and Erin Drive to realign lane markings.

Traffic during construction

  • Two lanes (one in each direction) will stay open
  • Turning may slow traffic at times
  • Some access restrictions or detours will affect churches and neighbourhoods in the area

See a map of planned phases